BUILDING DEFECTS RECTIFICATION UPDATE 18.11.20

To all owners, You may have recently received correspondence on Premium Strata’s letterhead dated 23 October 2020 (copy attached). Despite being on Premium Strata’s letterhead, the letter was drafted by solicitors acting for the Opal Tower Owners Corporation, Project Lawyers. The letter requests that, in the event that you suspect there is a defect within … Continue reading BUILDING DEFECTS RECTIFICATION UPDATE 18.11.20

WARRANTY & ENGINEER CERTIFICATIONS 02.04.20

Dear All, Following on from the completion of the remediation works, please see attached the following for your reference: 20-year Structural Warranty as agreed with the Owners Corporation WSP Design Certification WSP Construction Works Certification Thank you, Icon Team 大家好, 修复工作已经全部完成,请参阅附加的以下内容 • 与业主立案法团协定的20年结构保修 • WSP设计认证 • WSP建筑工程认证 谢谢 Icon Team

DEFECT REPORTING 02.10.19

Dear All, As detailed in our post ‘Defect Reporting Update 19.07.19’, please utilise the attached ‘Defect Report’ form to report any building defects and issue to OpalTower.Defects@icon.co to ensure our onsite team can review and action promptly. Thank you, Icon Team DEFECT REPORT FORM

ACCOMMODATION CLAIMS UPDATE 21.05.19

Dear All, As per ongoing discussions with Owners, Tenants and Fair Trading the following changes are implemented to the accommodation claims policy for the yellow and pink units: Owner Investors (Landlords): As the unit is not occupiable during the rectification period, Icon will reimburse the Owner Investors (Landlords) direct for rental loss during this period … Continue reading ACCOMMODATION CLAIMS UPDATE 21.05.19

ACCOMMODATION CLAIMS UPDATE 05.03.19

Dear All, Please see below update: UPDATED STATUTORY DECLARATIONS Please find attached updated Statutory Declarations for both Owner Occupiers and Tenants. The forms were updated taking into consideration comments made from various stakeholders including: Owner Occupiers only – provide Council Rates or Strata Rates as proof of ownership in lieu of Contract of Sale. Remove … Continue reading ACCOMMODATION CLAIMS UPDATE 05.03.19

ACCOMMODATION UPDATE 15.01.19

As detailed in our post earlier today, WSP and Rincovitch have confirmed the building is ready to be re-occupied now that the stabilisation works have been completed. Cardno has requested additional concrete samples to validate previously provided test results prior to supporting a progressive re-occupation of the building. We anticipate having the results mid-week. Should … Continue reading ACCOMMODATION UPDATE 15.01.19