OPAL TOWER UPDATE 18.03.19

Dear All,

Please see below update:

BUILDING WORKS

The Level 16 strengthening works have been completed and inspected by Cardno on Friday, 15 March. As a result, the BLUE apartments as highlighted in the below schedule are now ready for re-occupation effective immediately.

To ensure residents have sufficient time to return, the accommodation allowance for BLUE apartments will be in place to the morning of Saturday, 23 March 2019.

To facilitate the re-occupation of the yellow and pink apartments, the final remediation works are required to be completed to affected Levels 4, 10 and 16 sky gardens. Works can commence once the necessary approval has been issued by the Owners Corporation which will require a Special Resolution to be approved via an Extraordinary General Meeting (EGM).

The WSP drawings reflecting the final remediation works was issued to Strata Sense on 19 February 2019 and has been approved by Cardno. All information as required to issue the EGM notification has been provided by Icon with the expectation that works will be commencing by the end of March.

Kind Regards,

Icon Team